BMPP and Microsoft Project to Conquer Planning and Scheduling

To enhance project planning, Edwards has established a process: Big Monster Piece of Paper (BMPP). BMPP uses a structured, top-down brainstorming approach to develop a detailed project work plan.

Planning & Scheduling

January 2016

Inputs

The BMPP inputs include all project scope documentation, such as:

  • Contractual data (statement of work, notes, requirements)
  • Proposal (all volumes – technical, management, cost)
  • Proposal schedule, negotiation notes, reports, and requirements/design documentation; additional inputs including the technical knowledge of the project team, project manager, and subject matter experts (SMEs)

Tools, Ingredients, and Environments

Utilize a large work area, preferably a big massive piece of paper, such as a 36” roll or smaller sheets taped together, or a large white board; sticky-notes in multiple colors and sizes, markers, tape, and large empty wall space…ideally in a location where the project team can work without distractions (e.g. a war room).

The group builds the WBS together, or refines it if a proposal draft exists. The group also builds out the resource requirements and identifies resource conflicts up front. Risks are identified and methods for avoiding, managing, or mitigating them evolve as the project is detailed. The team creates a level of detail everyone agrees is appropriate. The team will become a cohesive unit through integration and communication even before the project begins. The PM will already have buy-in because stakeholders, team members, and SMEs have actively participated in project development.

Advantages of BMPP

BMPP is advantageous as it is easier to see the whole picture when viewing a large wall covered with sticky notes as opposed to hovering over a computer screen. This allows the team to easily change the task order as well as insert or remove activities.

BMPP Process

BMPP process steps involve first marking your territory where deliverables are identified, recurring tasks are listed out, and high-level summary tasks are recorded. Task descriptions should be worded so they are understandable as stand-alone statements – exact details can be written in the work package. The tasks are continually built down to the lowest level; identifying relationships between tasks by physically drawing lines on the paper to connect the tasks (predecessor/successor relationships).

Next, milestones are identified and marked by using a diamond shape; for detail tasks, all pertinent information should be listed on the sticky note (e.g., start date, duration, amount of work, resource assignments, BOE, assumptions, dependencies). If there is not enough space, use an external piece of paper.

Once the details are reviewed with the project team, management, and stakeholders, the BMPP process is complete and the PM is ready to use a scheduling tool (e.g., Microsoft Project).

Outputs

The meeting’s outputs and results will include development of the:

  • Work Breakdown Structure (WBS) diagram (hierarchical diagram of tasks)
  • WBS dictionary (document clearly defining each activity)
  • Logic/network diagram

Role of the Project Manager

The PM’s role in this process is a facilitator/coach who will get the ball rolling; keep the ball rolling by invoking discussion; look out for scope creep, and stop the session when all the juice is squeezed out. The PM should listen actively and refrain from judgments. PMs should also challenge the team by asking probing and leading questions. “What if…?” “What happens when …?” “What else is needed…?” “Are you sure…?”

Schedule Development and Structure

First, transfer the BMPP data from the wall to the tool. Use tape to secure the sticky notes to your paper before taking it down from the wall and relocating it to the data entry area.

Through the BMPP, you have defined project structure and the tasks contain everything needed to enter them into the scheduling tool (e.g., task description, start date, duration, resources, allocations, predecessors, successors, notes).

The PM will create three main sections in the schedule: meetings and major milestones, which focuses on upper management and customer reporting – linking major activities/phases within detailed project schedules; the deliverables section, which lists all of the project deliverables – contractually to the customer and internally; and the project detail section – including the meat of the schedule, documentation development, and links to meetings, major milestones, and deliverables sections. Each resource should have the correct labor rates, nonworking times, special working hours, or material costs.

Schedule Baseline

Once the baseline is set, the planned start and finish dates are known, the planned cost or Budget At Complete (BAC) for the project and the value of each task is understood, and resource requirements are defined (shortfalls/conflicts will need to be managed going forward).

BMPP Summary

Teamwork and buy-in is paramount to planning a successful project schedule. Do not get too wrapped up in technology; sometimes the old manual method is best. Communication is the most important function of the project manager.

Take Note

  • When using Microsoft Project 2010 or 2013, Edwards recommends the user turns on the “Project Summary” task from the Format Tab.
  • As tasks are built into the schedule, the summary task function should be used to group related tasks and milestones.

Planning & Scheduling

January 2016

The BMPP makes it easier to see the big picture.
Team building occurs before project work ever begins.
Involving people who will do the work in planning facilitates project buy-in and task ownership.
No systems or software is required for BMPP – just paper, pens, pads, and people.

Want to read more?

The Edwards Bookshelf

Our whole library on one shelf. Every book opens a different collection of free guides, real stories, videos, and classes.

Point at a book to peek inside. Click to open it.Tap any book to open it.